The Congolese State provides 435 million dollars for the effective relaunch of mining activities at MIBA. The investment of these millions of dollars is spread over 5 years, including 161 million for the first two years of the five-year term and the difference in the next three years.
While waiting for the first installment of the investment budget, MIBA intends to timidly start mining the kimberlite from the Massif 1 site in the first two years of the five-year term. This kimberlite will be fed to the three processing plants to be operationalized sequentially, and having a CUP of 0.49. Based on the CUP of the factories and the fleet of available machines, we have sized the machine park for the partial relaunch of mining activities. This machine park will consist of 2 probes, 3 excavators, 2 loaders, 6 trucks, 1 dozer, 1 grader, 1 compactor, 200-meter-long piping in place of a tanker truck, a machine refueling pump on site, movable on board a vehicle and safety equipment.